A) Water Management Terms for the Drawing up of the Main
Project
Along with a request for issuing water management terms, an
investor also submits some basic details on the location, the
purpose and size of the facility, and, when necessary, all
previous studies and notional plans which cast closer light on
the effects of the facility on water regime:
1. A copy of the plan (including the exact location of the
facility drawn) – issued by the Cadastre of Real Property
which has the jurisdiction;
2. Technical description of the planned works including the
planned facilities drawn in onto a cadastre – topographic
background;
3. A statement from land registry books (for the cadastre
allotment on which the facility is being built) – which is
issued by the Municipal Court that has jurisdiction, or by
another authority body;
4. A certificate on resolved property issues:
- an evidence of ownership-beneficiary right of the investor
over the land in case of building permanent facilities,
- an assent from the PWMC providing the construction of the
facility is of public interest on water ground,
- a contract on temporary usage of the land, when temporary
facilities on water ground are being built with respect to
article 16 of
the Decision on the Drainage Fee, the Irrigation Fee, the Fee
for the Utilisation of Water Management Facilities and for
Providing Other Services in 2008;
5. The plan of the area assignment – issued by the Municipal
Department of Urban Development which has jurisdiction;
6. The Position of the National Hydro-Meteorological Office,
66 Kneza Viseslava Street, Belgrade on the hydrological
conditions (water regime) on the location where the facility
is being built; and
7. The Position – issued by the regional Public Communal
Company on the effects on the waterworks and sewage facilities
and plants.
In case water management terms are requested for the drawing
up of project documentation for the extraction of sand and
gravel from watercourses, the following should be submitted
along with a Request:
1. Technical description;
2. Area situation;
3. Position of the National Hydro-Meteorological Office, 66
Kneza Viseslava Street, Belgrade; and
4. Position of the institution "Plovput", 9 Francuska Street,
Belgrade (for navigable rivers)
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to, if
necessary, complete the documentation. PWMC "Srbijavode"
issues a Decision or a Position, depending on the jurisdiction
given by the Law on Waters. In case this PWMC issues a
Position, the Decision is to be obtained from the Ministry of
Agriculture, Forestry and Water Management – the National
Directorate for Waters, 22 – 26 Nemanjina Street, Belgrade.
Along with the request, the Position of the PWMC and all
required documentation with respect to the Book of Regulations
("Official Gazette of the Republic of Serbia", No. 3/78)
should be submitted.
B) Water Management Assent to the Main
Project
1. Decision on the Issuing of Water Management Terms;
2. Main Project;
3. Technical check-up of the Main Project; and
4. Documents required for the Decision on the Issuing of Water
Management Terms.
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to
complete the documentation. Prior to issuing the water
management terms and assent, the Investor, when necessary, and
for the purposes of water area utilisation, utilisation of
water management facilities and provision of other services
(in accordance with the Decision for the ongoing year), signs
a suitable Contract with this Company or the Ministry of
Agriculture, Forestry and Water Management – the National
Directorate for Waters, 22 – 26 Nemanjina Street, Belgrade
(with respect to the official Ruling).
C) Water Management Approval (permit)
1. Decision on the Issuing of Water Management Assent;
2. The Minutes of the Commission for Technical Examination of
the Constructed Facility;
3. The Minutes of the National Water Management Inspection
(when the decision on water management approval is issued by a
PWMC);
4. Signed Contracts with this PWMC; and
5. Documents required in the Decision on the Issuing of Water
Management Assent.
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to
complete the documentation. As with the case of water
management terms, a Decision or Position can be issued
depending on the jurisdiction specified by the Law on Waters.
In the event that the Company issues a Position, the Decision
should be obtained from the Ministry of Agriculture, Forestry
and Water Management – the National Directorate for Waters, 22
– 26 Nemanjina Street, Belgrade. Along with the request, the
Position of the PWMC and all required documentation with
respect to the Book of Regulations ("Official Gazette of the
Republic of Serbia", No. 3/78) should be submitted. Water
management approval is issued with a period of validity for up
to 10 years, and it is required to prolong its validity before
it expires.
C1) Prolongation of the Validity of the
Water Management Approval
1. Details on the amounts of water scooped and drained
(periodical readings of the water gage at the water scoop and
drainpipe);
2. Analysis of the quality of the water at the drainpipe –
issued by official Agencies;
3. Evidence of paying the fee; and
4. The Minutes of the National Water Management Inspection
(when the decision on water management approval is issued by a
PWMC).
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to
complete the documentation.
D) Special Terms for the Drawing up of
Urban Development Plans
1. Situational representation of the area featuring the border
included in the plan drawn in;
2. Technical description of the planned works and facilities;
and
3. Terms of the Public Communal Company "Vodovod i
kanalizacija" which has the jurisdiction.
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to
complete the documentation.
E) Special Terms for the Drawing up of a
Notional Plan
1. Situational representation of the area featuring the site
of the planned facilities drawn in;
2. Technical description of the planned works and facilities;
and
3. Terms of the Public Communal Company which has the
jurisdiction.
In case some other documents are required, which will depend
on the particularities of the facility, the Investor will,
having submitted the request, subsequently be notified to
complete the documentation. |